Manchester's 136 apartment School Street plan is back tonight
The Shingle Hill plan, 136 apartments on 23.7 wooded acres off School Street, returns for its eighth Conservation Commission session. The commission can only rule on wetlands, not on the housing itself. The town's peer reviewer and the state have both sent the developer lists of fixes.

Trust Check: Checked against public records
The Manchester-by-the-Sea Conservation Commission meets tonight, Tuesday, Nov. 24. The biggest item is one it has taken up seven times since June: the 136 apartment building planned for the wooded hill at 0 School Street. The town calls the land Shingle Hill. The developer calls the project The Sanctuary at Manchester-by-the-Sea. On Nov. 4 the commission put the hearing off to tonight at the developer's request. (Read what happened on Nov. 4.)
This page explains, in plain words, what the commission is deciding, what it is not deciding, how the project got here and how to attend and speak.
Tonight
- WhenTuesday, Nov. 24, 6:30 p.m. The School Street hearing is the first item on the agenda, which the town clerk received Nov. 19.
- WhereOnline only, on Zoom. Join at us06web.zoom.us/j/81424876986, meeting ID 814 2487 6986, passcode 324760. By phone: 301 715 8592, then the meeting ID.
- The itemNotice of Intent, MassDEP file 039-0953, 0 School Street. The agenda also lists the same filing under "Orders of Conditions (if hearing is closed)," so the commission could close the hearing and vote on the permit tonight if it is ready to. Also back: the Pine Street wetland boundary filing on Gordon College land, the Tucks Point sailing docks and two Central Street items in the riverfront area.
- Who is dueThe town's peer reviewer, Tighe & Bond, and the developer's team, according to the Nov. 4 meeting.
- Also on the agendaApproval of the Sept. 22 and Oct. 13 minutes, a pre construction review for the Essex County Club, peer review updates and enforcement follow ups. The commission's next meeting is Dec. 15.
What is on the table
The developer, SLV School Street LLC of Needham, has filed a Notice of Intent. That is the form a landowner files when work will happen in or near a wetland. The commission holds a public hearing and then issues an Order of Conditions, a written permit with rules the work must follow, or denies it.
The plan, as the June 6 filing describes it:
- One three story building, 92,560 square feet, with 136 apartments and a parking garage underneath. The developer's 2021 application lists 220 garage spaces and 16 surface spaces.
- A driveway in from School Street, a pump house for sewer, retaining walls, drainage and landscaping.
- The building sits on the northern hill, outside the wetland buffer zones, about 300 feet from Sawmill Brook at its closest point.
- Parts of the driveway, the pump house and the drainage system fall inside the 100 foot buffer zone around wetlands and the 200 foot riverfront area along Sawmill Brook. That is why the commission has a say.
- About 13 acres on the southern part of the land would stay undisturbed. The developer's team told the commission on June 30 that about 8 acres, 34 percent of the parcel, would be disturbed in all.
Where the site is
Zoom and drag. Use the Aerial button to see the woods, Sawmill Brook to the west and Route 128 along the south edge. Streets shows School Street and the neighborhoods. The outline is approximate.
Parcel outline (approximate)
Outline: MassGIS property tax parcels, Map 43 Lot 18, simplified. Aerial: MassGIS. Streets: OpenStreetMap contributors. The building, driveway and wetland lines are in the filing and are not drawn here.
What the Conservation Commission can and cannot decide
This is not a vote on whether 136 apartments get built. That question was settled by the state. Manchester's Zoning Board of Appeals denied the project's comprehensive permit in 2022. A comprehensive permit is the single permit a developer can seek under the state's Chapter 40B law when at least a quarter of the homes are affordable. The developer appealed to the state's Housing Appeals Committee, and the committee overturned the denial, according to the developer's filing and the commission's June 30 minutes.
Because of that, the developer says the project needs no approval under the town's own wetlands bylaw. It is asking only under the state Wetlands Protection Act. The commission's chair said the same on June 30: the commission's job here is limited to the state law, and traffic, schools, public safety and taxes are outside its reach.
It can
- Decide whether the driveway, pump house and drainage work near the wetlands meet the state law's rules, including the state stormwater standards.
- Write conditions into the permit: erosion controls, monitoring wells, plantings, invasive plant rules, construction limits.
- Deny the Order of Conditions if the work does not meet the state rules.
- Keep the hearing open and ask for more information, as it has done since June.
It cannot
- Say no to the housing itself, the number of units or the building's size.
- Apply the town's own wetlands bylaw or its local stormwater rules to this filing.
- Take up traffic, schools, taxes or police and fire costs.
- Change the wetland lines. Those were fixed by a 2021 order, extended to May 25, 2027.
Under the state law, once the hearing closes the commission has 21 days to issue its written order. The developer, the town, an abutter or any 10 residents can then ask MassDEP to review the order within 10 days.
How it got here
| Date | What happened | Source |
|---|---|---|
| Wetland lines | ||
| Sept. 25, 2020 | The developer files to have the wetland lines on the whole parcel confirmed (an Abbreviated Notice of Resource Area Delineation). | NOI booklet, p. 4; town 40B page |
| May 25, 2021 | The Conservation Commission issues the order fixing the wetland lines. It was extended July 10, 2024, and runs to May 25, 2027. | NOI booklet, p. 4 |
| The housing permit | ||
| Sept. 16, 2021 | MassHousing issues a project eligibility letter, the first step in a Chapter 40B application. | Town 40B page |
| Sept. 27, 2021 | SLV applies to the Zoning Board of Appeals for a comprehensive permit: 136 apartments, 34 of them affordable. | Town 40B page; Project Data Summary |
| Oct. 26, 2021 to July 28, 2022 | The ZBA holds its public hearing over 16 sessions. | HAC decision, p. 1 |
| Aug. 16, 2022 | The ZBA votes 5 to 0 to deny the permit, citing the single steep access road and the environment. The written decision is dated Aug. 25 and filed Aug. 30. | Town 40B page; HAC decision |
| Sept. 15, 2022 | SLV appeals to the state Housing Appeals Committee. | Town 40B page |
| March 3 to 5, 2024 | The committee holds three days of hearings in town to cross examine witnesses, after a site visit Nov. 8, 2023. | HAC decision, p. 1 |
| Dec. 3, 2024 | Date on the committee's decision. The developer's June 2026 filing says the committee overturned the denial and gives the date as late 2025. | HAC decision; NOI booklet, p. 9 |
| The wetlands permit, 2026 | ||
| June 6, 2026 | SLV files its Notice of Intent with the Conservation Commission, under the state law only. | NOI booklet, p. 1 |
| June 30 | Session 1. The developer's team presents. Members ask for cut and fill volumes, a construction timeline, tree counts and whether the southern 13 acres will be permanently protected (no such plan yet, the team says). Continued, 6 to 0. | Minutes |
| July 21 | Session 2. Two peer review bids are in: Weston & Sampson, $15,800, and Tighe & Bond, $10,000. Members want a wider scope: vernal pools during construction, road salt, lighting, retaining walls. Continued, 6 to 0. | Minutes |
| Aug. 11 | Session 3. The commission hires Tighe & Bond on its updated Aug. 6 proposal, $15,000 lump sum. All contact between the reviewer and the developer goes through the conservation office. Continued, 5 to 0. | Minutes; proposal |
| Sept. 2 | MassDEP assigns file number 039-0953. It writes that the stormwater design "does not currently meet the Stormwater Standards." It also asks whether about 3,400 feet of sewer line and 3,700 feet of water line are part of the filing. | MassDEP letter |
| Sept. 8 | Session 4. Continued at the developer's request while the peer review goes on, 5 to 0. | Minutes |
| Sept. 22 | Session 5. On the agenda; minutes not yet posted. | Agenda |
| Oct. 13 | Session 6. The agenda notes the developer asked to continue to the next meeting. | Agenda |
| Oct. 30 | Tighe & Bond sends its peer review letter: 52 numbered comments. | Peer review letter |
| Nov. 4 | Session 7. Continued to Nov. 24 at the developer's request, unanimous. The peer reviewer and the developer are to attend. | Meeting video; our notes |
| Nov. 24 | Session 8, tonight, 6:30 p.m. on Zoom. First item on the agenda, and listed again under Orders of Conditions in case the hearing closes. | Agenda |
Votes are as the minutes record them. One commission member has stepped aside from this item and does not vote on it, saying he has an interest in a neighboring property.
What the reviewers found
Two sets of outside eyes have now looked at the plan. Both say the stormwater design needs work before it meets the state's stormwater standards, the 10 rules that say how a project must treat and soak in rain runoff.
| Standard | What it covers | Status |
|---|---|---|
| 1 | No new untreated discharge that erodes wetlands | Partly met show runoff speeds in a 2 year storm |
| 2 | Peak flows no higher than today | Partly met report and model do not match |
| 3 | Recharge, soaking water back into the ground | Met but the math needs fixing |
| 4 | Removing 80 percent of suspended solids | Not met pretreatment and forebays missing |
| 5 | Land uses with higher pollutant loads | Not met depends on fixing Standard 4 |
| 6 | Critical areas: Sawmill Brook and the vernal pools | Met more analysis on vernal pool volumes asked |
| 7 | Redevelopment sites | Not applicable |
| 8 | Erosion control during construction | Not met no plan provided yet |
| 9 | Long term operation and maintenance plan | Partly met add manufacturer manuals |
| 10 | No illegal discharges | Met |
Source: Tighe & Bond peer review letter, Oct. 30, 2026, comments 17 to 26. The plain words for each standard are ours; the status is the letter's.
The peer reviewer also raised bigger questions. It says the site's groundwater data comes mostly from test pits. It asks for permanent monitoring wells, a groundwater model and a mounding study. The reason: the plan soaks a lot of water into ground with shallow bedrock, steep slopes and vernal pools nearby. It asks the developer to show that the soaking areas are not in old fill from the land's past as a sand and gravel pit. It found four invasive plants on the site and wants truck washing and an invasive species plan. And it notes a wastewater treatment facility that appears only on the landscape sheets, with a connection that would cross a wetland.
MassDEP's Sept. 2 letter made some of the same points. It also asked for emergency shutoff valves in the drainage system because it discharges near certified vernal pools, and it suggested trucking excess snow off site rather than piling it at the edges.
A vernal pool is a small pond that fills in spring and dries in summer. Frogs and salamanders breed there because fish cannot live in it. The filing counts six on the land, several certified by the state. Sawmill Brook, just north of the site, is listed by the state as a coldwater fishery.
How to attend and speak
Get the agenda
The Nov. 24 agenda is on the town's Agenda Center. It lists the 6:30 p.m. start, the Zoom link, the meeting ID and the passcode, and says each item is generally limited to about 20 minutes.
Join on Zoom
The commission has met online only this year. Join a few minutes early. Keep your microphone off until the chair opens public comment on the School Street item.
Speak to what the commission can decide
Comments about wetlands, the brook, the vernal pools, drainage, erosion and construction get weighed. The chair has said traffic, schools, taxes and public safety are outside the commission's reach on this filing. The agenda says each item is generally limited to about 20 minutes, though this one has run longer.
Send it in writing
Written comments go to the conservation office: Conservation Agent Bethany Barstow, [email protected], 978-525-6435, Town Hall, 10 Central St. Letters already sent are posted on the town's 40B Proposals page. Office hours are Tuesday 8:30 a.m. to 5 p.m. and Thursday 8:30 a.m. to 6:30 p.m.
Read the file first
Everything the commission has is on the 40B Proposals page. That includes the 437 page Notice of Intent, the 24 site plan sheets and the drainage report. MassDEP's letter, the peer review letter and the public comments are there too.
Where to find the records
- 40B Proposals page, the Conservation Commission's file on the project
- Tighe & Bond peer review letter, Oct. 30 and MassDEP's Sept. 2 letter
- Town 40B Project page, the Zoning Board of Appeals file and the appeal timeline from 2021 to 2024
- Housing Appeals Committee decision, No. 2022-14
- Conservation Commission page and Agenda Center
Earlier coverage: Manchester conservation board puts the 136 apartment School Street hearing off to Nov. 24 (Nov. 6), our notes from the Nov. 4 meeting; Before Manchester's boards meet: a hearing on 136 apartments off School Street (Oct. 12), the Oct. 13 preview; Manchester sends housing plan to the state, hears smaller Pine Street apartment plan (Sept. 30), where the Select Board corrected the town housing plan to list this project at 136 units.
How we did this: Cape Ann Current read the developer's Notice of Intent, the peer review and MassDEP letters, the commission's 2026 agendas and minutes and the town's 40B pages. We also read the state Housing Appeals Committee decision and the MassGIS parcel record, and watched the town's Nov. 4 meeting video. These are our notes, not the commission's minutes. The time, Zoom details and item list are from the Nov. 24 agenda the town clerk received Nov. 19; a later amended agenda could change them. Corrections: [email protected].
Sources
- RecordTown of Manchester-by-the-Sea: 40B Proposals page (0 School Street, Shingle Hill: NOI booklet, site plans, drainage report, MassDEP comment, peer review proposals and letter, public comment)
- RecordSLV School Street LLC: Notice of Intent for 0 School Street (Map 43, Lot 0-18), Goddard Consulting LLC, June 6, 2026 (437 pages)
- RecordTighe & Bond: Technical and Permitting Peer Review, The Sanctuary at Manchester-by-the-Sea, 0 School Street, Oct. 30, 2026
- RecordMassDEP Northeast Regional Office: Notification of Wetlands Protection Act File Number 039-0953 with comments, Sept. 2, 2026
- RecordTighe & Bond: Shingle Hill 40B Project Peer Review Proposal, updated Aug. 6, 2026
- RecordTown of Manchester-by-the-Sea: 40B Project page (Shingle Hill timeline: project eligibility letter, ZBA application, hearings, denial, appeal)
- RecordSLV School Street LLC: Project Data Summary, comprehensive permit application to the Zoning Board of Appeals, 2021
- RecordMassachusetts Housing Appeals Committee: SLV School Street LLC v. Manchester-by-the-Sea Zoning Board of Appeals, No. 2022-14, decision dated Dec. 3, 2024
- RecordTown of Manchester-by-the-Sea: Conservation Commission minutes, June 30, 2026
- RecordTown of Manchester-by-the-Sea: Conservation Commission minutes, July 21, 2026
- RecordTown of Manchester-by-the-Sea: Conservation Commission minutes, Aug. 11, 2026
- RecordTown of Manchester-by-the-Sea: Conservation Commission minutes, Sept. 8, 2026
- RecordTown of Manchester-by-the-Sea: Conservation Commission agenda, Sept. 22, 2026
- RecordTown of Manchester-by-the-Sea: Conservation Commission agenda, Oct. 13, 2026
- RecordTown of Manchester-by-the-Sea: Conservation Commission amended agenda, Nov. 4, 2026
- RecordTown of Manchester-by-the-Sea: Conservation Commission amended agenda, Nov. 24, 2026 (received by the town clerk Nov. 19; 6:30 p.m., Zoom, School Street first under public hearings and again under orders of conditions, next meeting Dec. 15)
- RecordTown of Manchester-by-the-Sea: Conservation Commission meeting video, Nov. 4, 2026 (town YouTube channel)
- RecordTown of Manchester-by-the-Sea: Conservation Commission page (members, office hours, contacts, what the commission does)
- RecordTown of Manchester-by-the-Sea: Agenda Center (Conservation Commission agendas and minutes)
- RecordMassGIS: Standardized Property Tax Parcels, Manchester-by-the-Sea Map 43 Lot 18 (0 School Street, 23.72 acres, fiscal 2027 assessor data)
- RecordMassachusetts General Laws, Chapter 131, Section 40 (the Wetlands Protection Act)