Rockport's Blacksmith Shop gets $500,000 from the state

Cape Ann Works plans a restaurant, a cooking school and housing for workers in the old landmark on Mount Pleasant Street. The grant comes two months after town minutes said the work had run out of money.

Line drawing of the street side of the Blacksmith Shop in Rockport. A long new dormer with four windows is shaded pink on the roof. Notes point to cedar shingles, restored windows, a balcony and the sign over the front doors.
The street side of the Blacksmith Shop at 21 to 23 Mount Pleasant St. in Rockport, as drawn in Cape Ann Works' plans. The pink area is the new dormer on the third floor. The finished building may differ. Illustration: Drawing: Cape Ann Works

Trust Check: Checked against public records

The state is giving $500,000 to the project to bring back the Blacksmith Shop in Rockport.

The money goes to Cape Ann Works, the nonprofit that owns the old restaurant at 21 to 23 Mount Pleasant St. The group plans a year round restaurant, a cooking and hospitality school, and apartments for workers upstairs.

The grant lands at a key time. In September, the chair of Rockport's Historical Commission said she had been told the project was out of money. In October, the commission heard the group was waiting on a grant.

Gov. Maura Healey's office announced the award Thursday. It is one of 46 tourism grants across Massachusetts, worth $8.375 million in all. Only two of the 46 are bigger.

At a glance
  • The grant$500,000 from the Massachusetts Office of Travel and Tourism, for "The Blacksmith Shop Restaurant and Residency."
  • Who gets itCape Ann Works, a Rockport nonprofit that trains and places local workers.
  • The planA restaurant on the main floor run by students in training, teaching kitchens, and three apartments above for workers.
  • The buildingMore than 7,000 square feet on a 2,630 square foot lot at the edge of Rockport Harbor. The town values it at $2,086,400.
  • Where it standsThe cafe next door is open. Work on the main building began this spring. No opening date has been given.

What Cape Ann Works wants to build

The Blacksmith Shop was a well known Rockport restaurant for decades. Cape Ann Works says the building then sat empty and neglected for more than 15 years.

The group bought it in the spring of 2025. Its lawyer told the Zoning Board of Appeals that the building will work as a culinary school. Students will run a working restaurant on the main floor as part of their training.

The upper floors are for housing. The building has two apartments now. The zoning board approved a third, in what used to be a function room.

Cape Ann Works says the full job will turn the building into professional kitchens, dining rooms and apartments for workers. Its website says the old forge is still there and will be a feature near the entrance.

The first step is already open. The Blacksmith Shop Cafe opened in the old bakery at 21 Mount Pleasant St. with a ribbon cutting on July 9, 2025. Cape Ann Works says the cafe gives paid jobs and coaching to 20 local high school and college students.

The group says it hopes to welcome its first year round cooking class in 2027.

The approvals so far

The project needed a yes from several town boards. Here is how that went.

The Blacksmith Shop, step by step
  • March 4, 2025The Select Board voted 5 to 0 to let Cape Ann Works use a small piece of town land next to the building. Taxes and fees owed to the town had to be paid first.
  • Spring 2025Cape Ann Works bought the building.
  • May 7, 2025The Conservation Commission signed off on an emergency cleanup. Part of a floor had collapsed and debris fell toward the harbor. The minutes blame raccoons.
  • July 9, 2025The Blacksmith Shop Cafe opened.
  • Oct. 23, 2025The Historical Commission approved the outside changes, with conditions.
  • Oct. 29, 2025The Zoning Board of Appeals approved seven special permits. The vote was unanimous.
  • Spring 2026Construction began.
  • June 4, 2026The Historical Commission said the chimney had been taken down. Its approval called for the chimney to stay.
  • Sept. 24, 2026The commission's chair said she was told the project was out of money.
  • Nov. 19, 2026The state announced the $500,000 grant.

The zoning board needed seven special permits because the building does not fit today's zoning. The lot is 2,630 square feet. Zoning there calls for 5,000. The building is 36.1 feet tall, and the limit is 30. It sits less than 2 feet from the lot line on each side.

The new dormers on the front and back will not rise above the roof that is there now. The board had approved a similar plan for the building in February 2021, under an earlier owner.

The project's contractor is also the chair of the zoning board. The minutes show he ran that night's meeting but did not sit on this case. Five other members heard it and voted.

The chimney, and the money

The Historical Commission has kept the project on its agenda since May.

In June, the commission said the building's chimney had been removed. Its approval last fall said the chimney was to stay and have its brick joints repaired. The contractor told the chair the chimney was in very poor shape. He said it would be rebuilt to the same size.

The chair asked Cape Ann Works for a new application for the chimney. She asked for the size, the brick and the mortar. The commission's minutes from June, July and August say it was still waiting for an answer.

On Sept. 24, the chair told the commission she had been told informally that the project was out of money. On Oct. 1, the commission had not decided whether to send a formal violation letter.

By Oct. 22, there was some movement. The minutes say the group's director emailed on Oct. 7 that she believed she had the chimney measurements. A commission member said the director told her the project was waiting on grant money.

From the Historical Commission's minutes, Sept. 24

The chair "was informally told" that "the project is out of money."

Eight weeks later, the state announced a $500,000 grant for the project.

The state grant was not the only money the group went after. In June, Rockport's town administrator said his office was helping Cape Ann Works apply for a second state grant, from a program for underused buildings. The town has not said how that one turned out.

Where the grant comes from

The money is from the Destination Development Capital Grant Program. The state says the program pays to build, expand, restore or fix up places that draw visitors.

This round offered up to $8 million. Applications were due Aug. 11. The state said projects in cultural districts would get a closer look. The Blacksmith Shop is in Rockport's cultural district.

Cape Ann got two of the 46 awards. The Essex Historical Society and Shipbuilding Museum will get $25,000 for a project called "Building a Four Season Destination."

Two awards are larger than Rockport's. The EcoTarium in Worcester and The Cape Playhouse in Dennis each got $1 million. The Huntington Theatre Company in Boston also got $500,000. The average award was about $182,000.

Showing all 46 awards.

State tourism grants announced Nov. 19, 2026
EcoTariumWorcester$1,000,000Early childhood science and nature learning center exhibit
The Cape PlayhouseDennis$1,000,000Artist housing
Cape Ann Works Cape AnnRockport$500,000The Blacksmith Shop Restaurant and Residency
Huntington Theatre CompanyBoston$500,000Huntington East Wing construction
Armenian Museum of AmericaWatertown$400,000Accessibility and visitor experience at the museum
Provincetown Art Association and MuseumProvincetown$400,000Climate resilient building systems
Museum of ScienceBoston$350,000Riverview Cafe renovation
Sterling and Francine Clark Art InstituteWilliamstown$325,000Lunder vehicle bridge repair
The Wayside Inn FoundationSudbury$275,000Generator and water project
Jacob's Pillow Dance FestivalBecket$250,000New restroom pavilion
Berkshire Botanical GardenStockbridge$200,000The Glass House
Essex Agricultural SocietyTopsfield$200,000Topsfield Fairgrounds infrastructure and electrical improvements
Historic New EnglandNewbury$200,000Visitor and accessibility improvements at Spencer-Peirce-Little Farm
Rose Kennedy Greenway ConservancyBoston$200,000Lantern Stories
Discovery MuseumActon$175,000Office building reconstruction
Nantucket Historical AssociationNantucket$175,000Emergency generators
Town of EdgartownEdgartown$175,000Osborn's Wharf rehabilitation
Mechanics HallWorcester$150,000Audio and visual modernization
Western Massachusetts Climbers CoalitionErving$150,000Farley Ledge parking lot and trailhead
Chinese Consolidated Benevolent Association of New EnglandBoston$125,000Chinatown Immigrant Heritage Center
Boston BalletBoston$100,000Theater equipment
Eastern States ExpositionWest Springfield$100,000Strategic master plan
Eric Carle MuseumAmherst$100,000Climate resilient gallery systems
Esplanade AssociationBoston$100,000Smith Family Pavilion and Charlesbank Campus
Head of the Charles RegattaCambridge$100,000Connected Mobility Initiative
Museum of WorcesterWorcester$100,000Visitor access and arrival improvements
New England Mountain Bike AssociationHancock and Lanesborough$100,000Shaker Ridge Trails
Plimoth Patuxet MuseumsPlymouth$100,000Clean energy engineering for the Hornblower Visitor Center
Town of ScituateScituate$100,000Scituate Harbor Park
Franklin County Agricultural SocietyGreenfield$75,000Regional tourism pavilion
New England Botanic Garden at Tower HillBoylston$75,000Fuller Drive pavement and drainage
The W.E.B. Du Bois Center for Freedom and DemocracyGreat Barrington$75,000Design for reuse of the historic Clinton A.M.E. Zion Church
Town of BarnstableBarnstable$75,000Hyannis wayfinding and branding
Berkshire Scenic Railway MuseumLenox$50,000Preservation and climate upgrades to the heritage train
City of North AdamsNorth Adams$50,000Heritage State Park landscape improvements
The Hanover Theatre & ConservatoryWorcester$50,000Network upgrade
Town of Middleborough Tourism CommitteeMiddleborough$50,000Oliver Estate entrance and visitor experience
Amherst Business Improvement DistrictAmherst$25,000Amherst Visitors Center improvements
Essex Historical Society and Shipbuilding Museum Cape AnnEssex$25,000Building a Four Season Destination
Greater Northampton Chamber of CommerceNorthampton$25,000Heating and cooling system
Greater Springfield Convention & Visitors BureauSpringfield$25,000Visitor information kiosk
JFK Hyannis MuseumBarnstable$25,000Security alarm and camera system
Nantucket Island Chamber of CommerceNantucket$25,000Holiday tree electrical work
Old Sturbridge VillageSturbridge$25,000Accessible transportation
Town of BelchertownBelchertown$25,000Lake Wallace and Foley Field visitor parking
Town of LeeLee$25,000Lee 250 heritage tourism project
All 46 awards$8,375,000

Source: Commonwealth of Massachusetts, Executive Office of Economic Development and Office of Travel and Tourism, Nov. 19, 2026. Unit: dollars awarded. Largest first. Some project names are shortened. The state's list does not say how each award will be spent.

Dru Tarr, who won the state representative seat for Gloucester, Rockport and Essex this month, shared the news on Facebook on Monday. He congratulated Cape Ann Works.

Who is Cape Ann Works

Cape Ann Works began in 2022 as a pilot program. Local businesses could not find enough workers. State Sen. Bruce Tarr, town leaders, the Cape Ann Transportation Authority and Discover Gloucester helped start it.

In its first summer, the group says, it brought in more than 50 students from other countries and signed up more than 50 local students for seasonal jobs. It set up housing and bus routes for them.

It has since become a nonprofit. Its office is in the Blacksmith Shop building.

If you want to see it
  • WhereThe Blacksmith Shop Cafe, 21 Mount Pleasant St., Rockport, at the edge of the harbor.
  • What it servesCoffee, breakfast sandwiches, pastries, soups and paninis.
  • Phone978-525-8921
  • More on the projectblacksmithrockport.com

What is not known yet

Cape Ann Works has not said what the whole project will cost, how the $500,000 will be spent or when the restaurant will open. The state's list does not say either. The Historical Commission's minutes do not show a new chimney application yet.

Earlier: the Historical Commission on Oct. 1 and on Oct. 22.