Know Before It's Decided

Gloucester zoning board OKs a Western Avenue teardown over a neighbor's objections and puts the Maplewood Avenue stormwater fix off to Dec. 10

Four members approved every request before them on Nov. 12, from a Western Avenue rebuild in a flood zone to a 13 room lodging house on Eastern Point Road, but held the Maplewood Avenue housing project's drainage change until the city has every document in writing.

Chart: the nine decisions of the Gloucester Zoning Board of Appeals on Nov. 12, 2026. Approved 4 to 0: 27 Addison St. two family to three family, 81 Western Ave. teardown and rebuild, King Philip Road accessory dwelling unit, Honeysuckle Road shed, Keystone Road accessory building, Keystone Road access other than frontage, Highland Court addition, 28 Eastern Point Road lodging house to 13 units. Continued to Dec. 10: 50R Maplewood Ave. stormwater change.
What the Zoning Board of Appeals decided on Nov. 12, from the city's meeting recording. Votes are from the meeting video until the board's minutes confirm them. Cape Ann Current illustration

Trust Check: Checked against public records

Gloucester's Zoning Board of Appeals said yes to everything that came before it on Thursday, Nov. 12, except the one case it had already put off twice. The board approved a teardown and rebuild at 81 Western Ave. over a neighbor's objections, cleared the way for a 13 room lodging house on Eastern Point Road and granted six smaller requests, each by a vote of 4 to 0, from the meeting video. It put the Maplewood Avenue housing project's stormwater fix off to Dec. 10 so the city can get every plan and condition in writing first.

Four members sat: Chair Joseph Parisi III and Lauren Norton in the room at the Rose Baker Center for Aging Well, and Michael Nimon and Peter Cannavo on Zoom. The meeting started about 11 minutes late while the board waited for a quorum, and ran 2 hours 4 minutes.

9cases heard, 8 approved and 1 continued, all 4 to 0, from the meeting video
44.3%lot coverage approved at 81 Western Ave., where the zoning limit is 35 percent
3.5 feethow far too high the Maplewood Avenue stormwater tanks went in, by the developer's account
Dec. 10when the Maplewood Avenue change and the board's next meeting come back

What happened

  • 81 Western Ave.: 81 Western Ave. Realty Trust may tear down a two family house and build a one family house that covers 44.3 percent of a small lot in a flood zone. The next door neighbor, a civil engineer, said the plans disagree with each other and the coverage is really 51.4 percent. The board approved the request with one condition: the surveyed site plan governs.
  • 50R Maplewood Ave.: The board did not vote on Bigelow Real Estate LLC's request to change its approved drainage plan after the underground tanks went in about 3.5 feet too high. The city's outside reviewer said an added pump will work for storms up to the 25 year storm. The city's general counsel asked the board to wait until every document is in hand, and the board continued the case to Dec. 10.
  • 28 Eastern Point Road: 28 Eastern Point LLC may renovate a lodging house into 13 lodging units with no apartments, for up to 26 guests, and two special permits from 1970 were updated or rescinded.
  • Addison Street: A two family house becomes a legal three family house with two parking spaces instead of three.
  • Six smaller requests were approved: an accessory dwelling unit on King Philip Road, a shed on Honeysuckle Road, a storage building on Keystone Road, driveway access on Keystone Road, an addition on Highland Court and the Eastern Point lodging house above.

81 Western Ave.: a rebuild in a flood zone

The owner's attorney said the lot is very small, like its neighbors on that stretch of Western Avenue, and sits in a FEMA flood zone (the AE zone, where flood insurance maps expect water in a 100 year storm). The new house would be 30 feet tall with a basement and two floors, keep almost the same footprint, add garage space and change the building from two units to one. Lot coverage would go from 32.7 percent to 44.3 percent, where the zoning rules allow 35 percent.

The neighbor who lives next door told the board he had prepared plans like these for many years as a professional civil engineer, and that this application has "incorrect information, insufficient information, and insufficient substantiation." He said the submitted plans show 51.4 percent lot coverage, not 44.3; that the two plan sets put the deck 2 feet apart; that no building height appears on the elevations; and that the wrong flood map was used. He asked the board to deny the three requests so the trust could come back with a complete, consistent filing.

The attorney answered that the surveyed site plan is the accurate one and the architect's drawings were done from his office. Parisi said the board rules only on the footprint, lot coverage and setbacks, not height; that the second story balconies are exempt from setbacks; and that the city's flood zone reviewer had already found the increase in the flood zone did not reach 10 percent. Nimon said he was surprised the attorney had not answered the 44 versus 51 question, and asked that the decision say the site plan prevails if the two plan sets conflict. The board agreed and voted 4 to 0, from the meeting video, for a special permit to demolish and rebuild a nonconforming structure and two variances, for lot coverage and for building in the AE zone.

Maplewood Avenue: the pump is agreed, the paperwork is not

The 50R Maplewood Ave. housing project was approved under Chapter 40B, the state law that lets affordable housing projects get one comprehensive permit from the zoning board instead of separate local approvals. The board heard in October that the underground stormwater detention tanks were installed about 3.5 feet higher than the approved plans, with their bottoms at about elevation 42 instead of 38.5. Read what happened Oct. 8.

On Thursday the developer's attorney asked the board to adopt the as built plan plus one more change: a new pump, in a chamber on the 50R lot behind the lowest catch basin, which sits by the neighboring 7-Eleven lot. The pump would keep that basin draining into the tanks during storms up to the 25 year storm, the standard the original permit required. He said the developer still does not know how the tanks ended up too high.

The city hired Weston & Sampson to review the fix. Its engineer told the board the pump should work as described through the 25 year storm, that larger storms could still pond water behind the 7-Eleven lot for about 18 hours after the pumps run, and that the plan as originally approved would have ponded less in those bigger storms. Nimon said the board should not now demand a standard it never demanded before. The developer's engineers said the pump station has alarms, text alerts to the maintenance company and an on site generator.

An attorney for the owner of the neighboring property said his client favors the drainage fix but that the cross easements for drainage, parking and access that the board wrote into the permit three years ago have never been put in place. His engineer, who said he had met with the city engineer that afternoon, suggested the new pump's riser could be set a little higher in the chamber.

The city's general counsel asked the board to hold its vote until it has every final document, including the plan showing the new pump and the operation and maintenance manuals, so "everybody knows what they have to comply with." Weston & Sampson's engineer asked for two conditions: a revised as built plan after the work, and an updated operation and maintenance plan covering the new pump. The developer agreed to both. Parisi said he wants everything "in writing together" and a vote at the next meeting, with the public hearing already closed. The board voted 4 to 0, from the meeting video, to continue the case to Dec. 10.

Eastern Point Road: a lodging house gets a new permit

28 Eastern Point LLC asked to renovate a lodging house on a 22,885 square foot lot in the R-10 zone. Its attorney said the building now has 8 lodging units, an efficiency apartment and an owner's unit under a city lodging house license for 8 rooms and 23 guests. The plan rebuilds it as 13 lodging units with no apartments, for up to 26 guests, with a wheelchair ramp, a larger front entry, a bigger dormer and new windows and doors. The building is already taller than the zone allows; the height would go from 33.2 feet to 34 feet. There would be 14 parking spaces, one per room plus one for every three employees.

Two special permits from 1970 were in the way: one for a six room guest house with 11 occupants, the other for a third floor apartment. The board voted 4 to 0, from the meeting video, for a special permit to alter and expand the nonconforming building, to modify the 1970 guest house permit to allow 13 units and 26 guests, and to rescind the apartment permit. No one spoke for or against.

The other six

  • 27 Addison St.: The owners said the house had been used as a three family for years before they bought it and they want to make it legal; a sprinkler system is already in. The board granted a special permit to convert from two to three units, a variance to have two parking spaces instead of three and a variance for lot area per unit and a 10 foot front yard where 15 is required.
  • King Philip Road: A homeowner may build an accessory dwelling unit with a garage under it between the house and the road, closer to the street than the main house, because the rest of the lot is a ridge of solid ledge that would need blasting.
  • Honeysuckle Road: A shed may go in the back corner of a corner lot with variances from the front yard and side yard setbacks. Nimon asked that the written decision state how far from the lot lines the shed can sit, and the chair said the building inspector will add the dimensions.
  • Keystone Road, accessory building: A metal storage building for a classic car and tractors, with no water, sewer or heat, got variances for being closer to the street than the house and for the 8.1 foot distance between buildings, and a special permit for a height over the 12 foot limit for accessory buildings.
  • Keystone Road, access: A homeowner who reaches his house by a shared driveway over a neighbor's lot under a recorded 2010 easement got a variance to keep using it instead of his legal frontage. The chair said this lets the owner give up that frontage and carve off a new house lot, which would go to the Planning Board as an approval not required plan.
  • Highland Court: An East Gloucester corner lot gets a second floor on top of an existing one story addition and a new rear deck, with a special permit to alter a nonconforming structure and a variance for lot coverage.

What was decided, Nov. 12

ItemVote
Consent agenda: chair to sign the decisions for 55 Holly St. and 2 High Rock Ter.4 to 0, from the meeting video
27 Addison St.: special permit, two family to three family; variances for two parking spaces, lot area per unit and front yard setback4 to 0, from the meeting video
81 Western Ave. Realty Trust: special permit to demolish and rebuild; variances for lot coverage and building in the AE flood zone; site plan governs4 to 0, from the meeting video
50R Maplewood Ave., Bigelow Real Estate LLC: change to the comprehensive permit drainage planContinued to Dec. 10, 4 to 0, from the meeting video
King Philip Road: variance for an accessory dwelling unit closer to the street than the house4 to 0, from the meeting video
Honeysuckle Road: variances for a shed in the front and side yard setbacks4 to 0, from the meeting video
Keystone Road: variances for an accessory building's distance to the street and to the house; special permit for its height4 to 0, from the meeting video
Keystone Road: variance to reach the lot other than over its legal frontage4 to 0, from the meeting video
Highland Court: special permit for a second floor addition; variance for lot coverage4 to 0, from the meeting video
28 Eastern Point LLC: special permit to alter and expand; modify the 1970 guest house permit to 13 units and 26 guests; rescind the 1970 apartment permit4 to 0, from the meeting video

Roll call votes of Nimon, Cannavo, Norton and Parisi, as heard on the city's recording. Not yet confirmed by the board's minutes.

What happens next

Dates to watch

  • Thursday, Dec. 10, 7 p.m. The board's next meeting. The Maplewood Avenue drainage change comes back for a vote with the public hearing closed, so no new testimony is taken. Eastern Point Yacht Club's event hosting request, continued from Oct. 29, is also due that night.
  • After the Dec. 10 meeting. Written decisions on Thursday's approvals go out, and each can be appealed within the time the state zoning law allows.
  • Keystone Road. Any new lot would need an approval not required plan from the Planning Board.

Where to find the records

Earlier coverage: Tonight in Gloucester: five stores appeal flavored tobacco fines, and the zoning board returns to the Maplewood Avenue stormwater fix (Nov. 12), the agenda for this meeting; Hammond Castle loses its appeal (Nov. 1), the Oct. 29 meeting; Gloucester zoning board hears 7 new requests Thursday (Oct. 28); and Gloucester housing project's stormwater tanks went in about 4 feet too high (Oct. 21), the Oct. 8 meeting.

How we did this: Cape Ann Current watched the meeting online on the city's recording. Votes are as heard on the recording and are labeled from the meeting video until the board's minutes confirm them. These are our meeting notes, not the board's minutes.

See something wrong? Email [email protected]. Read our standards and corrections policy.