Did you know? Gloucester's Magnolia Avenue bridge sign reads 13 feet 6
That is nine inches lower than the sign on the Essex Avenue bridge where a truck got stuck Monday. The city's public works director has said the real opening is taller than the sign.

Trust Check: Checked against public records
Gloucester: Did you know the sign on the Magnolia Avenue railroad underpass says 13 feet 6 inches? That is nine inches lower than the sign on the Essex Avenue railroad bridge, where a truck got stuck on Monday.
The two bridges are about a quarter mile apart in West Gloucester. The same railroad line crosses both roads.
But the sign may not tell the whole story. The city's public works director has said he thinks the real opening on Magnolia Avenue is taller than the sign says.
| What else to know | ||||
|---|---|---|---|---|
| Essex Avenue railroad bridgeRoute 133. Red circle on the map | 14 ft 3 in | 9 inches | NoAbout 300 feet past the Magnolia Avenue turn | Where a truck got stuck on Monday, Nov. 23. On Route 133, the way to and from downtown Gloucester. |
| Magnolia Avenue railroad underpassYellow circle on the map | 13 ft 6 inOn the sign. The public works director said in 2025 he thinks the real height is about 14 ft 4 in | NoneAbout 10 inches if the real height is 14 ft 4 in | YesEvery heavy truck to or from Kondelin Road passes under it | 22 feet wide, in an S-curve. The road under it was dug lower in the early 1970s. It floods. |
Tap a column heading to sort. Massachusetts law sets the truck height limit at 13 feet 6 inches. Sources: MassDOT sign inventory (Essex Avenue). Board of Health hearings, May 29 and June 4, 2025, and decision, June 18, 2025 (Magnolia Avenue).
Where the 13 feet 6 inches comes from
It comes from the sign on the bridge.
A traffic engineer told the city's Board of Health about it on May 29, 2025. He said he went to the underpass on May 5, 2025. He said he measured the road under it at about 22 feet wide, and that the underpass is signed at 13 feet 6 inches.
That number is also the state limit. Massachusetts law says a truck can be no taller than 13 feet 6 inches without a special permit.
The real height may be more
A week later, on June 4, 2025, Public Works Director Mike Hale was asked at the same hearing what the clearance is. He said he thinks it is about 14 feet 4 inches.
Hale said 13 feet 6 inches is a standard number that truck drivers look for on overpasses. It tells them a tractor trailer can fit.
If he is right, the Magnolia Avenue underpass and the Essex Avenue bridge are about the same height. The Essex Avenue signs say 14 feet 3 inches. We found no measured clearance for either bridge in the documents we read.
The road was dug lower so trucks could fit
Hale told the board the road under the bridge used to be a couple of feet higher. He said it was lowered in the early 1970s so trucks could reach the industrial park. He said he has city memos from 1968 to about 1971 that work out how far the road had to drop to make room for a truck 13 feet 6 inches tall.
That fix left a low spot. Hale said the underpass floods often, anywhere from twice a month to once every six months. He said the water can be a couple of feet deep and that he has seen the road closed for hours, half a day or a full day.
Why it matters now
Magnolia Avenue is the only way in for heavy trucks going to the Cape Ann Industrial Park on Kondelin Road. It is also the truck route for the construction waste station proposed at 24 Kondelin Road. The Board of Health's decision says trucks over 2.5 tons can reach that site only from Magnolia Avenue north of Kondelin Road, through the underpass.
The city's traffic reviewer counted 389 heavy vehicles a day on that part of Magnolia Avenue. With the station, the reviewer's number is 538.
Monday's crash was not on that route. The Essex Avenue bridge is about 300 feet past the turn onto Magnolia Avenue. But it showed what one stuck truck does. Police closed Essex Avenue during the morning commute.
Read more in our story on the truck route and our full look at the proposal.
Questions worth asking
- What is the measured clearance under each bridge today, and when was it last checked?
- Who owns and inspects the two bridges?
- How tall are the trucks and containers that would use the waste station?
- What is the plan when the underpass floods and heavy trucks have no other way in?
We watched the Board of Health hearings online. The heights in this story are the heights on the signs, except where we say otherwise.
Sources
- RecordGloucester Board of Health hearing, May 29, 2025, city recording (traffic engineer: underpass signed at 13 feet 6 inches, about 22 feet wide)
- RecordGloucester Board of Health hearing, June 4, 2025, city recording (Public Works Director Mike Hale: real clearance, the early 1970s lowering of the road, flooding)
- RecordGloucester Board of Health: Site Assignment Decision, Eastern Waste Services LLC, 24 Kondelin Road, June 18, 2025
- RecordMassDOT sign inventory: Low Clearance signs reading 14 feet 3 inches, Essex Avenue (Route 133) eastbound mile 39.0 and westbound mile 39.1, Gloucester (signs recorded Oct. 2014)
- RecordMassachusetts General Laws, Chapter 90, Section 19 (vehicle height limit of 13 feet 6 inches)
- RecordGloucester Police Department (Official) on Facebook: Traffic Alert, Essex Avenue (Nov. 23, 2026)
- SourceGoogle Maps: aerial imagery for the marked up map
Do you trust this story?
See something wrong? Email [email protected]. Read our standards and corrections policy.